US Washington Data Center Maintenance and Upgrade
Scheduled Maintenance Report for Presslabs
Completed
The scheduled maintenance has been completed.
Posted Jan 14, 2020 - 12:45 EET
Update
All production sites are online. Development instances are now starting up as well.
Posted Jan 14, 2020 - 11:58 EET
Update
All servers have been successfully upgraded. We're now starting to boot-up all sites in this cluster.
Posted Jan 14, 2020 - 11:27 EET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 14, 2020 - 06:30 EET
Update
We will be undergoing scheduled maintenance during this time.
Posted Jan 13, 2020 - 20:31 EET
Update
We will be undergoing scheduled maintenance during this time.
Posted Jan 13, 2020 - 20:30 EET
Scheduled
Between Monday and Tuesday night, the US Washington cluster will be upgraded with new state-of-the-art infrastructure. During this time for approximately 4 hours the back-end servers will be offline making the wp-admin area and all dynamic requests of the public sites to be inaccessible.

After this maintenance, your service will run on a state-of-the-art infrastructure which ensures that you will be able to continue to rely on our infrastructure for years to come.

Please note that all cached public sites and media files will continue to be accessible, the cache and database will be frozen with ~15 minutes before the shutdown.

If you have any questions regarding this maintenance please send us an e-mail at support@presslabs.com

Full time frame of the shutdown below:

Date: January 13, 2020 - January 14, 2020
Time: 23:59 EST (UTC-05:00) - 04:00 EST (UTC-05:00)
Posted Jan 10, 2020 - 15:53 EET
This scheduled maintenance affected: Public Websites.